Network Analysis (CPM and PERT)

JKSSB Junior Engineer (Civil) · Construction Planning and Management · 27 practice questions with answers and explanations: 16 Easy, 8 Medium, 3 Hard.

Sample questions

Sample Easy question 1

The total float of an activity is:

  1. Earliest finish minus latest start
  2. Latest start time minus earliest start time
  3. Duration minus the earliest start
  4. Earliest start minus latest finish
Show answer

Answer: B. Total float = LST − EST, which also equals LFT − EFT.

Sample Easy question 2

Free float is the delay possible in an activity without affecting:

  1. The earliest start of the succeeding activity
  2. The latest finish of the project
  3. The project cost
  4. The critical path
Show answer

Answer: A. Free float is the spare time that does not disturb the following activity.

Sample Easy question 3

A dummy activity in a network:

  1. Is always on the critical path
  2. Consumes no time or resource and shows a logical link
  3. Consumes time but no resource
  4. Shows the final activity
Show answer

Answer: B. Dummies keep the logic of the network correct.

Sample Medium question 4

The activities on the critical path have variances of 4, 9, 1 days². The standard deviation of the project duration is about:

  1. 7.48 days
  2. 3.74 days
  3. 14 days
  4. 1.87 days
Show answer

Answer: B. σ = √(4 + 9 + 1) = √14 = 3.74 days.

Sample Medium question 5

The latest event time of an event is 18 days and its earliest event time is 14 days. The event slack is:

  1. 4 days
  2. 32 days
  3. 18 days
  4. 14 days
Show answer

Answer: A. Slack = TL − TE.

Sample Medium question 6

The latest finish time of the last activity is 12 days and its duration is 3 days. The latest start time is:

  1. 9 days
  2. 15 days
  3. 3 days
  4. 12 days
Show answer

Answer: A. LST = LFT − duration.

Sample Hard question 7

In a network, A (4 days) is followed by B (6 days) or C (5 days) in parallel, and then by D (3 days). The project duration is:

  1. 10 days
  2. 13 days
  3. 12 days
  4. 18 days
Show answer

Answer: B. The critical path A-B-D takes 4 + 6 + 3 = 13 days, and A-C-D takes 12.

Sample Hard question 8

An activity takes 10 days at a normal cost of ₹10,000 and 7 days at a crash cost of ₹16,000. Its cost slope is:

  1. ₹2,000 per day
  2. ₹1,000 per day
  3. ₹6,000 per day
  4. ₹3,000 per day
Show answer

Answer: A. Slope = (16,000 − 10,000) ÷ (10 − 7) = ₹2,000 per day.

Sample Hard question 9

A network has two paths to its final event: A (2 days), C (5 days), E (3 days) and B (4 days), D (4 days), E (3 days). The project duration is:

  1. 10 days
  2. 13 days
  3. 11 days
  4. 21 days
Show answer

Answer: C. Path A-C-E takes 10 days and path B-D-E takes 11 days. The longer, 11 days, is the critical path.

More Construction Planning and Management topics for JKSSB Junior Engineer (Civil)