Industrial Engineering
JKSSB Junior Engineer (Mechanical) · Industrial Management and CAD/CAM · 13 practice questions with answers and explanations: 0 Easy, 13 Medium, 0 Hard.
Sample questions
Sample Medium question 1
Method study aims at:
- measuring the time of a job
- fixing the wages of workers
- estimating the cost of material
- finding the best and easiest way of doing a job
Show answer
Answer: D. Method study records and examines methods to develop a better one.
Sample Medium question 2
A stop-watch time study is used to determine the:
- profit of a firm
- number of workers needed in a year
- standard time for a job
- breakdown cost of a machine
Show answer
Answer: C. Observed times are rated and allowances added to get the standard time.
Sample Medium question 3
At the break-even point:
- total revenue equals total cost
- profit is maximum
- fixed cost is zero
- variable cost is zero
Show answer
Answer: A. Neither profit nor loss is made at the break-even point.