Dams, Spillways and River Training

JKSSB Junior Engineer (Civil) · Irrigation Engineering · 19 practice questions with answers and explanations: 13 Easy, 4 Medium, 2 Hard.

Sample questions

Sample Easy question 1

Compared with an earth dam, a masonry or concrete gravity dam needs:

  1. A weaker foundation
  2. A clay core
  3. A strong foundation, usually rock
  4. No foundation
Show answer

Answer: C. The high concentrated loads of a gravity dam need a sound rock foundation.

Sample Easy question 2

Uplift pressure under a gravity dam:

  1. Reduces the effective weight of the dam
  2. Increases the stability
  3. Has no effect on stability
  4. Acts only on earth dams
Show answer

Answer: A. Drainage galleries are provided to reduce it.

Sample Easy question 3

The phreatic line in an earth dam is the:

  1. Line of the spillway crest
  2. Top line of seepage within the embankment
  3. Line of maximum pressure
  4. Bottom of the foundation
Show answer

Answer: B. The downstream slope should stay above the point where it emerges.

Sample Medium question 4

A gravity dam has a total vertical force of 6,000 kN, a horizontal thrust of 3,000 kN and a coefficient of friction of 0.7. The factor of safety against sliding is:

  1. 1.4
  2. 0.71
  3. 2
  4. 0.35
Show answer

Answer: A. FS = μ ΣV ÷ ΣH = 0.7 × 6,000 ÷ 3,000 = 1.4.

Sample Medium question 5

The resisting moment of a dam about its toe is 12,000 kN·m and the overturning moment is 6,000 kN·m. The factor of safety against overturning is:

  1. 6,000
  2. 0.5
  3. 3
  4. 2
Show answer

Answer: D. FS = resisting moment ÷ overturning moment.

Sample Medium question 6

A pan evaporimeter shows an evaporation of 8 mm in a day, and the pan coefficient is 0.7. The lake evaporation is:

  1. 2.8 mm
  2. 5.6 mm
  3. 11.4 mm
  4. 8 mm
Show answer

Answer: B. Lake evaporation = pan coefficient × pan evaporation.

Sample Hard question 7

By the rational formula Q = C I A ÷ 360, with C = 0.4, I = 60 mm/h and A = 50 hectares, the peak runoff is:

  1. 1,200 m³/s
  2. 3.33 m³/s
  3. 0.33 m³/s
  4. 6.67 m³/s
Show answer

Answer: B. Q = 0.4 × 60 × 50 ÷ 360 = 3.33 m³/s.

Sample Hard question 8

The discharge over an ogee spillway is Q = C L H^(3/2). With C = 2.2, L = 20 m and H = 1.5 m, Q is about:

  1. 161.7 m³/s
  2. 121.2 m³/s
  3. 66 m³/s
  4. 80.8 m³/s
Show answer

Answer: D. Q = 2.2 × 20 × 1.5^1.5 = 80.8 m³/s.