Sample Easy question 1
6 men can complete a work in 12 days. How many days will 8 men take?
- 10
- 11
- 8
- 9
Show answer
Answer: D. Total work = 6 × 12 = 72 man-days. For 8 men: 72/8 = 9 days.
Sample Easy question 2
A can finish a job in 8 days. After working for 4 days, what fraction of the job is done?
- 1/2
- 1/4
- 2/3
- 1/3
Show answer
Answer: A. In 4 days, A does 4/8 = 1/2 of the work.
Sample Easy question 3
If 5 workers can complete a task in 12 days, how many days will 10 workers take?
- 5
- 4
- 7
- 6
Show answer
Answer: D. Doubling the workers halves the time: 12/2 = 6 days.
Sample Medium question 4
A, B and C can complete a piece of work in 15, 24 and 60 days respectively. They start together. After 1 day A leaves, and after 3 more days C also leaves. In how many more days will B finish the remaining work?
- 17 4/5 days
- 15 4/5 days
- 16 4/5 days
- 18 4/5 days
Show answer
Answer: C. Work done in the first 1 day(s) = 1 × 1/8; work done in the next 3 day(s) by B and C = 3 × 7/120. Remaining work = 7/10, which B alone does in 16 4/5 days.
Sample Medium question 5
A, B and C can complete a piece of work in 20, 24 and 60 days respectively. They start together. After 2 days A leaves, and after 1 more day C also leaves. In how many more days will B finish the remaining work?
- 18 2/5 days
- 17 2/5 days
- 16 2/5 days
- 19 2/5 days
Show answer
Answer: B. Work done in the first 2 day(s) = 2 × 13/120; work done in the next 1 day(s) by B and C = 1 × 7/120. Remaining work = 29/40, which B alone does in 17 2/5 days.
Sample Medium question 6
A, B and C can complete a piece of work in 30, 20 and 15 days respectively. They start together. After 1 day A leaves, and after 1 more day C also leaves. In how many more days will B finish the remaining work?
- 16 2/3 days
- 14 2/3 days
- 13 2/3 days
- 15 2/3 days
Show answer
Answer: B. Work done in the first 1 day(s) = 1 × 3/20; work done in the next 1 day(s) by B and C = 1 × 7/60. Remaining work = 11/15, which B alone does in 14 2/3 days.
Sample Hard question 7
Together, A and B take 18 days to finish a job; A does half as much work as B in three-fourths of B's time. Find B's time alone.
- 25
- 30
- 28
- 32
Show answer
Answer: B. Working through the ratio gives A's rate as 2/(3x) where x is B's time; solving the combined rate equation gives x = 30 days.
More Mathematics topics for Ladakh Police Sub-Inspector
- Algebra
- Average
- Boats & Streams
- Data Interpretation
- Geometry
- HCF & LCM
- Height & Distance
- Mensuration
- Mixture & Alligation
- Number System
- Partnership
- Percentage
- Problems on Ages
- Problems on Trains
- Profit/Loss & Discount
- Ratio & Proportion
- Simple & Compound Interest
- Simplification & Approximation
- Surds & Indices
- Time, Speed & Distance
- Trigonometry